Our client contracted JIFMAR to perform the replacement of the flexible discharge line currently in use in client terminal. JIFMAR was in charge of the complete engineering & project management for this operation, which we already successfully carried out twice. The new 60m long flexible was assembled at quay & lifted afloat using 6 mobile cranes in parallel.
The Alexandre Z together with a team of divers disconnected the used flexible after flushing, and towed to site the newly assembled one. It was then immersed, connected to the in-place pipeline and pressure tested. Operations were carried out smoothly in 8 days, using the site’s knowledges of the JIFMAR team.