REPLACEMENT OF FLEXIBLE HOSE

Work performed

Our client contracted Jifmar to perform the replacement of the flexible discharge line currently in use in client terminal. Jifmar was in charge of the complete engineering & project management for this operation, which we already successfully carried out twice. The new 60m long flexible was assembled at quay and lifted afloat using 6 mobile cranes in parallel.

The Alexandre Z together with a team of divers disconnected the used flexible after flushing and towed to site the newly assembled one. It was then immersed, connected to the in-place pipeline and pressure tested. Operations were carried out smoothly in 8 days, using Jifmar Team’s site knowledge.

Project Informations

Equipment: ALEXANDRE Z / JIF EXPRESS
Location: PORT LA NOUVELLE - FRANCE
Contract Type: TURNKEY
Date Start & Stop: 2021
Work Operations: TOWING & SUBSEA WORK