Work performed

To reduce scour (water erosion) around a wind turbine monopile, Jifmar was contracted to install 405 sandbags around the monopile seabed.

Roxane Z, our DP2 multipurpose vessel was fitted with a hydraulic grab and realized the deployment of the bags within 15 days offshore Ramsgate. Maximum capacity on deck was of 58 bags (200kg each), a total of 7 rotation was needed to complete the full job.

Project Informations

Equipment: ROXANE Z
Location: UK
Date Start & Stop: 2019
Work Operations: Sand bags installation on monopile